Work item: HS2-EW-LM-Ph1-Ar-No-N1-Prog-works-39-16/12/2021

Work Item Summary

Project Phase
Phase 1
Region
Solihull
Location
A452, Berkswell
Worksite Name
A452 Kenilworth Road, Park Lane
Contractor
LM JV
Type of works
Construction, Road closure, Traffic management
Estimated Start Date
07/03/2022
Estimated End Date
13/03/2022

What we are doing

Please find below further dates for traffic management to support the construction of the roundabout on the A452 Kenilworth Road, Berkswell, close to Park Lane:

7, 8 & 9 March – Overnight road closures on the northbound carriageway 8pm to 6am. Wootton Lane will remain closed
from the A452. Please follow diversion.
10, 11, 12 & 13 March – Overnight road closures on the southbound carriageway 8pm to 6am. Park Lane access will be closed from the A452. Please follow diversion.
Ongoing until further notice – Single lane closures on both carriageways 24/7 with daytime working hours. Traffic management, including all signage, will be erected as and when required subject to consent, site and weather conditions.

Please keep an eye out for signage on the road as dates are also subject to change.
Further information:
Local diversions will be clearly signposted. Access for residents and businesses within the A452 closure will be maintained by approaching the traffic marshall at the relevant closure point.