Rotary piling and fencing, South Heath, Buckinghamshire
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Prog-works-08-16/07/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- South Heath
- Contractor
- Align JV
- Type of works
- Fencing, Piling
- Estimated Start Date
- 25/07/2024
- Estimated End Date
- 31/10/2024
What we are doing
Following on from the compound set up and mobilisation of works between South Heath and Leather Lane, we will soon begin to build the abutments and piers for two overbridges GMI/2 and GMI/12. To do this we will install rotary piles. A total of 18 rotary piles will be installed to create the foundations of the new overbridges. This work is not expected to create any significant noise or impact for residents.
We will also be replacing the current ‘post and rail’ fencing around our site with rigid mesh security fencing. This is for safety reasons as well as security and will be installed during daytime working hours. Landowners have been contacted to discuss the works and arrange timings that are suitable. Site hoarding already installed will not be changed.
Works will commence from the end of July to end of October 2024, from 8am to 6pm Monday to Friday. We don’t anticipate working Saturdays but may on occasion if required, from 8am to 1pm.