Severn Trent works – diversion route

Work item: HS2-EW-UT-Ph1=-Ar-No-N1-UT-20-16/07/2021

Work Item Summary

Project Phase
Phase 1
Region
Birmingham, West Midlands
Location
Birmingham
Worksite Name
Washwood Heath
Contractor
Severn Trent Water
Type of works
Utility works / surveys
Estimated Start Date
31/08/2021
Estimated End Date
29/10/2021

What we are doing

Severn Trent are carrying out utility diversion work in Duddeston Mill Road. A road closure will be in place on Duddeston Mill Road (highlighted in red on the below map) from 31st August 2021 until 27th September 2021, this will be followed by a lane closure with traffic lights from 27th September 2021 until 29th October 2021.