Sewer lining works on A40 Western Avenue

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-04/01/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
A40, Western Avenue
Worksite Name
A40
Contractor
SCS JV
Type of works
Sewer lining
Estimated Start Date
20/01/2024
Estimated End Date
22/01/2024

What we are doing

From Saturday 20 to Sunday 21 January 2024, we will be carrying out overnight works to install a temporary pipe which will allow the existing sewer pipe to be redirected. These works are in preparation of the main sewer lining works to strengthen and protect the existing sewage structure during HS2 tunnelling works.

These works will take place during two overnight shifts between 6pm and 6am.