Sewer lining works on Horsenden Lane South, January 2024

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-10/12/23

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, London
Location
Horsenden Lane South
Contractor
SCS JV
Type of works
Utility works / surveys
Estimated Start Date
08/01/2024
Estimated End Date
21/01/2024

What we are doing

From 8 to 21 January 2024, we need to carry out sewer lining works on Horsenden Lane South. This is following a ground movement assessment; the lining works are required to reinforce the existing Thames Water sewer.

These works will take place overnight, 9pm to 6am, Monday to Friday and on weekends if required. We will have traffic diversions in place during these works 24 hours a day.