Sewer lining works on Horsenden Lane South, January 2024
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-UT-1-10/12/23
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, London
- Location
- Horsenden Lane South
- Contractor
- SCS JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 08/01/2024
- Estimated End Date
- 21/01/2024
What we are doing
From 8 to 21 January 2024, we need to carry out sewer lining works on Horsenden Lane South. This is following a ground movement assessment; the lining works are required to reinforce the existing Thames Water sewer.
These works will take place overnight, 9pm to 6am, Monday to Friday and on weekends if required. We will have traffic diversions in place during these works 24 hours a day.