Sheet piling works in Euston Approaches

Work item: HS2-SCS-25-1314

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Hampstead Road
Worksite Name
Euston Approaches, Euston Throat
Contractor
SCS JV
Type of works
Sheet piling
Estimated Start Date
15/09/2025
Estimated End Date
13/10/2025

What we are doing

We are currently installing sheet piles on site between Hampstead Road bridge and our site office.

To minimise disruption, we have been using a quiet, non-vibratory rig to push the sheet piles into the ground. However, due to difficult ground conditions we haven’t been able to install all of the sheet piles using this method.

On Monday 8 September, we successfully completed a trial using a vibratory rig. As a result, we now plan to use this rig to install the remaining sheet piles which we expect to take about four weeks to complete.

This change in methodology is likely to result in higher noise and vibration levels, which may be noticeable to residents in the surrounding area. We apologise for any inconvenience caused.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]