Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Hampstead Road
- Worksite Name
- Euston Approaches, Euston Throat
- Contractor
- SCS JV
- Type of works
- Sheet piling
- Estimated Start Date
- 15/09/2025
- Estimated End Date
- 13/10/2025
What we are doing
We are currently installing sheet piles on site between Hampstead Road bridge and our site office.
To minimise disruption, we have been using a quiet, non-vibratory rig to push the sheet piles into the ground. However, due to difficult ground conditions we haven’t been able to install all of the sheet piles using this method.
On Monday 8 September, we successfully completed a trial using a vibratory rig. As a result, we now plan to use this rig to install the remaining sheet piles which we expect to take about four weeks to complete.
This change in methodology is likely to result in higher noise and vibration levels, which may be noticeable to residents in the surrounding area. We apologise for any inconvenience caused.