Single lane closures on Frith Hill, Great Missenden
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Prog-Works-14-07/03/2025
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Great Missenden
- Worksite Name
- Frith Hill
- Contractor
- Align JV
- Estimated Start Date
- 12/04/2025
- Estimated End Date
- 31/05/2025
What we are doing
Following on from previous cable testing works, UK Power Network (UKPN) will be conducting repair works to existing underground cables on Frith Hill and connecting power to our North Portal site. This requires two single lane closures along Frith Hill while works are underway.There will be one single lane closure which will be managed with temporary two-way traffic lights while the other with priority traffic system to ensure traffic flow is safely maintained. UKPN will send out their own notice prior to these works to confirm working hours.
Traffic management and works will take place between mid April and the end of May 2025.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]