Site and shutdown activity during the Christmas period 21 December – 2 January
Work item: HS2-MW-BBVS-Ph1-OOC-St-S4-CHR-13-12-2023ANL
Work Item Summary
- Project Phase
- Phase 1
- Region
- Old Oak and North Acton
- Location
- Old Oak Common lane
- Worksite Name
- Old Oak Common
- Contractor
- BBVS JV
- Type of works
- Ground investigations
- Estimated Start Date
- 21/12/2023
- Estimated End Date
- 02/01/2023
What we are doing
Most work at the station site will shut down at 6pm on 22 December and start up again at 8am on 2 January 2024.
While site activity is reduced and the conveyor is switched off, we will carry out strengthening activity to the conveyor foundations. This will take place on the station site, next to Old Oak Common Lane (see map on page 2 for the location). For safety reasons, to ensure there is an appropriate exclusion zone in place, this work is scheduled for when there is reduced activity on site.
The foundations will be excavated between 21 to 23 December 24 hours a day. We will use smaller excavators to minimise impact and sound barriers will be installed around the working zone to reduce noise from the machinery being used. Sound barriers will be installed around the working zone to reduce noise from the machinery being used.
We will carry out the strengthening and propping installation works, from 27 to 31 December. If required, some non-intrusive works such as excavation and backfilling with excavators might occur between 6pm and 6am.
See the notification attached for further information