Site enabling works in front of Cartmel
Work item: HS2-MW-SCS-Ph1-Ar-So-S1-Prog-works-18-09/02/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Hampstead Road, Regent's Park Estate
- Contractor
- SCS JV
- Type of works
- Early construction works, Ground investigations, Site clearance
- Estimated Start Date
- 20/09/2021
- Estimated End Date
- 10/12/2021
What we are doing
Site enabling works in front of Cartmel will include number of trial holes and surveys of Cartmel building foundations.
GPR surveys around Cartmel – 13 to 17 December
On week starting 13 December we will carry out ground penetrating radar (GPR) surveys in the area around Cartmel building, outside our worksite. A team of surveyors will use a small, wheeled machine to assess for underground structures and utility services in the area marked on the map below. These surveys will not be noisy, and we will carry them out during core hours over two or three days .
The details of above works are in the update notification below.
Download information relating to these works
- November update on Hampstead Road and site enabling works
- October update on site enabling works in front of Cartmel
- Site enabling works in front of Cartmel
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]