Site preparation and construction activities in Small Dean, Wendover

Work item: EKFB-Small Dean-Feb-2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Small Dean, Wendover
Contractor
EKFB JV
Type of works
Early construction works, Site clearance, Works affecting Public Rights of Way
Estimated Start Date
15/02/2021
Estimated End Date
31/03/2021

What we are doing

As our works continue to progress, we have been acquiring and taking possession of land along the line of route for various site preparation and construction activities. In the Small Dean area of Wendover, over the coming weeks there will be a variety of activities being undertaken.

There will be a temporary closure to the 1805 footpath from the A413, London Road through to Small Dean Lane. This closure allows us to fence and secure the area of HS2 possessed land while we undertake site preparation work for the Small Dean viaduct, this will include clearing some vegetation in the area.

Where vegetation and trees need to be removed it will be undertaken under the guidance of ecologists and arboriculturists.

The work will start from Monday 15 February 2021.

Some of the site clearance work which is necessary is within close proximity to the existing Chiltern Rail Line, there will be some work completed outside of our core working hours to allow for safe working access in and around the rail line.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]