SM24 footpath closure

Work item: HS2-EW-BBV-Ph1-Ar-No-N1-Prog-works-17-29/09/2020

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Long Itchington
Contractor
BBV JV
Type of works
PRoW Closure, PRoW diversion
Estimated Start Date
29/09/2020
Estimated End Date
31/12/2024

What we are doing

As you’ll be aware, a section of the A425 Leamington Road near Southam has now re-opened. However, the public right of way SM24 remains closed until end of 2024. This is to allow us to construct the ‘‘cut-and-cover’ section of the Long Itchington Wood Tunnel. We apologise for any inconvenience this may cause.

The section of the footpath which remains closed is marked orange on this plan. An alternative route is marked in green.