Spring Update: Works at Victoria Road Crossover Box and Flat Iron sites
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-27/02/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Victoria Road
- Worksite Name
- Victoria Road
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 01/03/2024
- Estimated End Date
- 31/07/2024
What we are doing
Works are continuing in the Victoria Road Crossover Box site to construct the ventilation shaft and crossover box. These structures will regulate air flow, provide access to the tunnels, and allow trains to switch tracks as they enter and leave the future Old Oak Common Lane station.
Works are now focused on finalising of the base slab and associated wall and structures following completion of the box excavation works.