Spring Update: Works at Willesden Euroterminal site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-22/02/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing
- Location
- Willesden Euroterminal
- Worksite Name
- Willesden Euroterminal site
- Contractor
- SCS JV
- Type of works
- Construction
- Estimated Start Date
- 05/03/2024
- Estimated End Date
- 31/07/2024
What we are doing
As the tunnelling programme progresses, we expect from April 2024 to manage rail activity for up to 35 train departures of excavated material a week, as well as continued delivery of the tunnel segment by rail.