Steeple Claydon construction activities February 2021

Work item: FUS_AWN_0180HS2-EW-Fusion -Ph1-Ar-Ce-C2-Prog-works-1-03/08/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Steeple Claydon
Contractor
EKFB JV, Fusion JV, WPD
Type of works
Early construction works, Environmental mitigation works, Utility works / surveys
Estimated Start Date
08/03/2021
Estimated End Date
12/03/2021

What we are doing

Before the main railway construction works for the realignment and
reconstruction of the new bridge commences on Addison Road, Fusion,
EKFB and Western Power Distribution need to undertake a number of
construction activities. To minimise disruption, the works have been
coordinated so that they can be undertaken under one road closure.
Activities include:
• Traffic management and localised removal of roadside
hedgerows and vegetation for future construction works
required for the new Addison Road overbridge (Fusion)
• Ground investigation survey works (EKFB)
• Diversion of two underground electrical high voltage circuits (WPD)

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]