Steeple Claydon construction activities February 2021
Work item: FUS_AWN_0180HS2-EW-Fusion -Ph1-Ar-Ce-C2-Prog-works-1-03/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Steeple Claydon
- Contractor
- EKFB JV, Fusion JV, WPD
- Type of works
- Early construction works, Environmental mitigation works, Utility works / surveys
- Estimated Start Date
- 08/03/2021
- Estimated End Date
- 12/03/2021
What we are doing
Before the main railway construction works for the realignment and
reconstruction of the new bridge commences on Addison Road, Fusion,
EKFB and Western Power Distribution need to undertake a number of
construction activities. To minimise disruption, the works have been
coordinated so that they can be undertaken under one road closure.
Activities include:
• Traffic management and localised removal of roadside
hedgerows and vegetation for future construction works
required for the new Addison Road overbridge (Fusion)
• Ground investigation survey works (EKFB)
• Diversion of two underground electrical high voltage circuits (WPD)
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]