Substation removal and footpath closure on Victoria Road, North Acton
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-20/05/2025
Work Item Summary
- Project Phase
- Phase 1
- Location
- Victoria Road
- Worksite Name
- Victoria Road Crossover Box
- Contractor
- SCS JV
- Type of works
- Footpath closures
- Estimated Start Date
- 04/06/2025
- Estimated End Date
- 28/06/2025
What we are doing
From Wednesday 4 June to Saturday 28 June 2025, we will be removing a substation within our Victoria Road Crossover Box site, during core working hours.
We will need to narrow the vehicle lanes and there will be a footpath closure for these works. A pedestrian diversion route will be in place on this section of Victoria Road between School Road and Victoria Road.
Traffic management will be in place at all times during these works. You may hear noise from machinery, such as an excavator, and hand tools. We will aim to minimise disruption where possible.