Summer Update: Victoria Road Ancillary Shaft Headhouse
Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-26/06/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Brent and Ealing, Old Oak and North Acton
- Location
- Victoria Road
- Worksite Name
- Victoria Road
- Contractor
- SCS JV
- Type of works
- Works Update
- Estimated Start Date
- 18/07/2024
- Estimated End Date
- 18/09/2024
What we are doing
From mid-July 2024 we will start work on the ancillary shaft headhouse. The headhouse will contain the safety controls and ventilation systems for the future railway tunnel below.
During the first phase of works, from18 July to 18 September 2024, we will drive piles into the ground to create a strong foundation for the concrete base of the headhouse.
Works will take place from 8am to 6pm Monday to Friday, and 8am to 1pm on Saturdays. There may be times when we will need to work outside these hours, and we will let you know in advance.