Summer Update: Victoria Road Ancillary Shaft Headhouse

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-26/06/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing, Old Oak and North Acton
Location
Victoria Road
Worksite Name
Victoria Road
Contractor
SCS JV
Type of works
Works Update
Estimated Start Date
18/07/2024
Estimated End Date
18/09/2024

What we are doing

From mid-July 2024 we will start work on the ancillary shaft headhouse. The headhouse will contain the safety controls and ventilation systems for the future railway tunnel below.

During the first phase of works, from18 July to 18 September 2024, we will drive piles into the ground to create a strong foundation for the concrete base of the headhouse.

Works will take place from 8am to 6pm Monday to Friday, and 8am to 1pm on Saturdays. There may be times when we will need to work outside these hours, and we will let you know in advance.