Survey equipment installation near Wilsmere Drive and Cartmel Court, Northolt

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-OTH-1-30/01/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Cartmel Court, Wilsmere Drive
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Ground monitoring equipment installation, Survey
Estimated Start Date
19/02/2024
Estimated End Date
23/02/2024

What we are doing

What we are doing
Under our current tunnelling programme, the first of our tunnel boring machines (TBMs) will reach the Northolt area by 10 March, and the second TBM due to arrive by 25 March. In advance of this time, we need to install ground monitoring equipment and fill in two boreholes in the open space behind Wilsmere Drive.

Small survey studs will be hammered into the ground between the pavement and the kerb which will only take a short while and remain in place for approximately two years.

A small team of operatives will be working with a portable concrete batcher, pump and concrete mix in the borehole locations and will place barriers around each. It may take up to three hours to fill each borehole. The barriers will remain in place until the subcontractor returns on the third day to ensure that the hole has been filled in correctly.

How these works might affect you

There may be some noise whilst we carry out these works. We would like to apologise in advance for the disruption or inconvenience this may cause. We will ensure that disruption is kept to a minimum with any noisy works kept to the core hours of 8am – 6pm.