Update on temporary boundary wall construction, South Ruislip Ventilation Shaft, Victoria Road

Work item: HS2-MW-SCS-Ph1-Ar-So-S1-Prog-works-35-06/07/2023_04

Work Item Summary

Project Phase
Phase 1
Region
Hillingdon
Location
South Ruislip
Worksite Name
South Ruislip
Contractor
SCS JV
Type of works
Hoarding works
Estimated Start Date
25/09/2023
Estimated End Date
06/10/2023

What we are doing

What we are doing – Construction of new boundary hoarding
We wrote to you in July to let you know that we would begin working on a temporary boundary wall at the back of our South Ruislip site.  Due to related works taking longer than anticipated, we will now be starting works these works on 25 September 2023.

We will be breaking out the original hoarding and expect that this will create some noise. These works will be undertaken 24/7, however noise monitoring will be in place at all times.

We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way. We will ensure that disruption is kept to a minimum and that regular updates are provided.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]