Temporary closure of Park Lane and Cappers Lane, Huddlesford
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-9-17/11/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Huddlesford, Lichfield
- Contractor
- BBV JV
- Type of works
- Haul road construction, Road closure
- Estimated Start Date
- 16/01/2023
- Estimated End Date
- 10/02/2023
What we are doing
We are constructing haul roads and accesses along the HS2 route. Haul roads are temporary roads provided within a working area to allow for the movement of construction materials, construction machinery and/or construction staff around the site. Haul roads are Balfour Beatty VINCI’s preferred logistical transport link, as they reduce the number of vehicle movements interfering with the existing local road network and provide the greatest possible control over works activity.
To commence building haul roads and accesses in this area we will be undertaking works along Park Lane and Cappers Lane. The works along Park Lane include a utility diversion and installing safety barriers across our excavation. We will follow these works by constructing an access to our working area off Cappers Lane.
We will complete these works from Monday 16 January 2023 to 10 February 2023. To carry out our works safely, we will install phased temporary closures of Park Lane and Cappers Lane, as below:
Park Lane – Monday 16 January to Friday 27 January 2023.
Cappers Lane- Monday 30 January to Friday 10 February 2023.
The temporary closures will be in place from 9:30am to 3:30pm each weekday.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]