Temporary closure of the layby, A5 Hints area
Work item: HS2-EW-BBV-Ph1-Ar-No-N2-Prog-works-13-06/01/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Hints
- Contractor
- BBV JV
- Type of works
- Road closure
- Estimated Start Date
- 05/07/2021
- Estimated End Date
- 09/07/2021
What we are doing
We will be undertaking ground investigation surveys on land at the side of the A5. These surveys help us to understand more about the ground conditions where we want to build the railway. The surveys will involve taking soil samples and boring trial holes in different locations. We will use a small number of 4×4 vehicles with trailers, to transport and set up equipment in the survey area.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]