Temporary closure of Welsh Road, Offchurch
Work item: HS2-EW-LM-Ph1-Ar-No-N1-Prog-works-13-06/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Offchurch
- Contractor
- LM JV
- Type of works
- Utility works / surveys
- Estimated Start Date
- 30/06/2021
- Estimated End Date
- 31/08/2021
What we are doing
LM is due to temporarily close and divert Welsh Road (between Long Itchington Road and B4455 Fosse Way), 24/7 from Wednesday 30 June until late August. This timeframe is subject to consents – any changes will be published on hs2inwarwickshire.co.uk.
This closure is needed to safely build a new utility corridor, involving an open trench on the road, which is expected to take around 8 weeks to finish.
A signed diversion will be in place, following Long Itchington Road and B4455 Fosse Way