Temporary footpath closure
Work item: FUS_AWN_0216 HS2-EW-Fusion -Ph1-Ar-Ce-C2-OTH-36-28/05/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Aylesbury
- Contractor
- Fusion JV
- Type of works
- Footpath closures
- Estimated Start Date
- 07/06/2021
- Estimated End Date
- 16/06/2021
What we are doing
Ahead of the main construction works in the former Aylesbury Golf Club site we will be continuing vegetation clearance around a number of the public right of ways.
For the safety of the pedestrian and personnel involved with the works, we will need to close the public rights of way whilst work is under way. We will need to close the footpaths each day between from 8:30am to 4:30pm. The footpaths will remain open outside of these hours.
Depending upon progress we will, where possible, provide a safe walking route along the footpath during this period of works. access to the public right of way will remain restricted during the two phases of works until work is complete. Signage will be erected advising of diversion routes.
Download information relating to these works