Temporary office facility at Vehicle Holding Area
Work item: HS2-EW-SCS-Ph1-Ca-S1-Prog-works-1-28/04/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Camden, Prince Albert Road
- Contractor
- SCS JV
- Type of works
- Worksite / compound set-up
- Estimated Start Date
- 24/05/2021
- Estimated End Date
- 12/06/2021
What we are doing
The Vehicle Holding Area is now nearing completion and will be operational from late May.
In May and June, due to social distancing measures, we will install additional temporary offices in the Vehicle Holding Area to accommodate our growing team until November. We will locate this two-storey welfare office between the park-side hoarding and the existing three-storey site office as shown in the map below. It will not be visible to residents once installed.
We will deliver the temporary cabins as large loads outside peak hours with traffic marshals to assist. We will deliver the first set of cabins in the week beginning 24 May, and the second set of cabins in the week beginning 7 June. We will use a crane to lift the cabins from the lorries into position within the site.
The welfare cabins will be The Royal Parks dark green colour, with white window frames.