Temporary, overnight lane closures along the A452 and A446, and overnight road closure along the A446, from Monday 29 November to Wednesday 1 December

Work item: HS2-21-68566-E

Work Item Summary

Project Phase
Phase 1
Region
Solihull, Warwickshire
Location
Bickenhill
Contractor
LM JV
Type of works
Lane closure, Road closure
Estimated Start Date
29/11/2021
Estimated End Date
01/12/2021

What we are doing

When the future HS2 Interchange Station is operational, four new highways bridges will connect the current road network to new routes we are creating. The second of these new highways bridges was safely installed in October 2020 over the A446. This year, we’ll carry out various activities to fully complete the construction of these brides including monitoring before ownership is handed over to the highways authority.

We’ll be starting work on Monday 29 November

To carry out this work safely, we’ll install temporary, overnight lane closures along short sections of the A452 northbound and A446 southbound, leading into a road closure along the A446 southbound and northbound from Monday 29 November to Wednesday 1 December. Our working hours will be 8pm to 6am.

A signed diversion route will be in place for road users during this road closure. Our contractors may be on site up to an hour before and after these times to set up and close down the site.