What we are doing
Carriageway works
We have now completed our main utility works on Bridgwater Road. Following these works, we need to undertake some resurfacing works to Bridgwater Road.
We will be closing Bridgwater Road from 17 to 30 July to carry out the following works:
• Replace kerbs
• Resurface footpath
• Resurface sections of the road
• Removing excavator from site compound on the playing field
A clearly signed diversion route will be in place.
The road will be closed from Carmichael Close to the access gates to the playing field. We will provide the parking bays that were in place before the works started.
We would like to apologise in advance for any disruption or inconvenience this may cause. Every effort is being taken to ensure that these works are carried out in the least impactful way.
We will ensure that disruption is kept to a minimum.