Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-11/01/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Park Village East
- Worksite Name
- Camden Cutting
- Contractor
- SCS JV
- Type of works
- Hoarding works
- Estimated Start Date
- 30/01/2023
- Estimated End Date
- 31/01/2023
What we are doing
On 30 and 31 January, we will close a section of Park Village East between Parkway and Mornington Street Bridge to carry out hoarding maintenance on the lorry lay-by. The road will be closed between 8am and 6pm both days, and open in the evenings and overnight.
Traffic will be diverted via Albany Street, Robert Street and Stanhope Street. We will maintain vehicle access for local businesses and residents. Vehicles may be delayed for a few minutes while we clear the road to allow them to pass. We apologise for any inconvenience this may cause.
Update: We previously informed you that UK Power Networks will install a substation within the lorry lay-by next to 1 Park Village East to provide power to our track-level worksite. The install will now take place from 8 February until early March.
For further details please see notification below.