Temporary road closure on Park Village East – 30 and 31 January

Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-works-1-11/01/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Park Village East
Worksite Name
Camden Cutting
Contractor
SCS JV
Type of works
Hoarding works
Estimated Start Date
30/01/2023
Estimated End Date
31/01/2023

What we are doing

On 30 and 31 January, we will close a section of Park Village East between Parkway and Mornington Street Bridge to carry out hoarding maintenance on the lorry lay-by. The road will be closed between 8am and 6pm both days, and open in the evenings and overnight.

Traffic will be diverted via Albany Street, Robert Street and Stanhope Street.  We will maintain vehicle access for local businesses and residents.  Vehicles may be delayed for a few minutes while we clear the road to allow them to pass. We apologise for any inconvenience this may cause.

Update: We previously informed you that UK Power Networks will install a substation within the lorry lay-by next to 1 Park Village East to provide power to our track-level worksite. The install will now take place from 8 February until early March.

For further details please see notification below.

Download information relating to these works