Temporary road closure – Station Road, Quainton

Work item: 1MC12-EKF-IN-NTE-CS08-000004

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Quainton
Contractor
EKFB JV
Type of works
Road closure, Vegetation clearance
Estimated Start Date
29/06/2021
Estimated End Date
02/07/2021

What we are doing

We need to carry out ecology surveys and vegetation clearance along
Station Road, Quainton.
All clearance works are undertaken under the instruction of the ecologist on
site, who decides the appropriate method of clearance based on the
vegetation present. This involves a detailed hand search to determine if any
ecology is present. If the area is found to be clear, then vegetation clearance
will take place.
A small workforce will use machinery and handheld equipment to clear
sections of vegetation. This will involve the use of brush cutters, chainsaws
and tractors, employing different methods to remove the area of vegetation.

Download information relating to these works

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]