Temporary single lane closure along the A446 northbound from Monday 22 November 2021 for three weeks
Work item: HS2-EW-LM-Ph1-Int-St-N3-Traf-12-11/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Solihull
- Location
- Bickenhill
- Contractor
- LM JV
- Type of works
- Environmental mitigation works, Lane closure, Tree planting
- Estimated Start Date
- 22/11/2021
- Estimated End Date
- 13/12/2021
What we are doing
To facilitate tree planting in the area, we will install a temporary single lane closure along a short section of the A446 northbound off Northway Island, from Monday 22 November for three weeks, from 9.30am to 3.30pm each day. We will work Monday to Friday. Our contractors may be on site up to an hour before and after these times to set up and close down the site at each location.
This schedule is subject to change depending on supply chain deliveries and gaining the appropriate consents.
These traffic measures will be carried out in conjunction with a new, permanent direction of travel for road users around Northway Island and occasional off-peak single lane closures around the longabout, on the way to the NEC, and along short sections of the B4438 and Northway.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]