Temporary traffic lights A429 Kenilworth Road
Work item: HS2-EW-BBV-Ph1-Ar-No-N1-Traf-38-26/08/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Kenilworth
- Contractor
- BBV JV
- Type of works
- Early construction works
- Estimated Start Date
- 13/09/2021
- Estimated End Date
- 31/10/2021
What we are doing
Temporary traffic lights will be in place on the A429 from 13 September to 31 October 2021 and will be operational between 8.00am and 6.00pm.
These lights will allow us to move our plant (including large machinery), material and personnel safely over the A429 whilst we operate a crossing. This is necessary as it supports our earthworks activity in this area. This work includes the construction of Kenilworth Cutting and a box structure which will allow the HS2 line to eventually go underneath the current railway. The lights are essential and allow us to complete the work as safely as possible.
During busier periods of the day these lights will be manually operated to aid the flow of traffic and reduce disruption.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]