Temporary traffic lights and construction update: Chesham Road

Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Traf-23-27/10/2021

Work Item Summary

Project Phase
Phase 1
Region
Buckinghamshire
Location
Great Missenden
Worksite Name
Chesham Road
Contractor
Align JV
Type of works
Traffic management
Estimated Start Date
11/11/2021
Estimated End Date
06/01/2003

What we are doing

This notice is to inform you of temporary traffic lights in place at Chesham Road. To enable caisson construction from mid November until summer. 2022 Working hours are 8am to 6pm Monday to Friday and 8am to 1pm on Saturdays.