View route map
Temporary traffic lights and construction update: Chesham Road
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Traf-23-27/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Buckinghamshire
- Location
- Great Missenden
- Worksite Name
- Chesham Road
- Contractor
- Align JV
- Type of works
- Traffic management
- Estimated Start Date
- 11/11/2021
- Estimated End Date
- 06/01/2003
What we are doing
This notice is to inform you of temporary traffic lights in place at Chesham Road. To enable caisson construction from mid November until summer. 2022 Working hours are 8am to 6pm Monday to Friday and 8am to 1pm on Saturdays.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]