Temporary traffic lights Ashow Road (B4113)
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-10-16/01/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Stoneleigh
- Contractor
- BBV JV
- Type of works
- Utility works / surveys, Vegetation clearance
- Estimated Start Date
- 23/01/2023
- Estimated End Date
- 16/02/2023
What we are doing
Updated notification – extension of works
We will be carrying out trial holes to support the design work as well as vegetation clearance and tree stump removals to clear the way for drainage works and the road re-alignment works.
We will need to install three-way temporary traffic lights, to ensure a safe working area while we install the plant crossing. These will be removed once the works are complete.
These works will take place 23 January and will now be completed on 16 February 2023, temporary traffic lights will be in operation 24 hours per day. Our working hours will be 8am to 6pm Monday to Friday and possibly 8am to 1pm on Saturday
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]