View route map
Temporary traffic lights: B485 Chesham Road, Buckinghamshire
Work item: HS2-MW-Align-Ph1-Ar-Ce-C1-Traf-21-14/12/2022
Work Item Summary
- Project Phase
- Phase 1
- Location
- B485
- Worksite Name
- Chesham Road
- Contractor
- Align JV
- Type of works
- Lane closure, Traffic management
- Estimated Start Date
- 16/01/2003
- Estimated End Date
- 20/01/2003
What we are doing
Two-way temporary traffic lights will be in place on Chesham Road, B485 From Monday 16 to Friday 20 January 2023, to allow UK Power Network to work in the carriageway to safely complete the mains electrical connection for Chesham Road site. This connection will provide power to the HS2 railway in the Chiltern tunnel when it becomes operational.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]