Temporary traffic lights on Gilson Road, Coleshill

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-44-06/06/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Coleshill
Contractor
BBV JV
Type of works
Vegetation clearance
Estimated Start Date
03/07/2023
Estimated End Date
14/07/2023

What we are doing

To continue our preparation for the construction of the HS2 railway, we will be carrying out topsoil stripping in areas close to Gilson Road.

In order to complete this work safely, we will install three-way traffic lights along a short section of Gilson Road and within our existing site access, from Monday 3 July until Friday 14 July. The location of the traffic management is shown in the map below. The traffic lights will be in place from 9.30am until 3.30pm, Monday to Friday.