Temporary traffic lights on Gilson Road, Coleshill
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-44-06/06/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Coleshill
- Contractor
- BBV JV
- Type of works
- Vegetation clearance
- Estimated Start Date
- 03/07/2023
- Estimated End Date
- 14/07/2023
What we are doing
To continue our preparation for the construction of the HS2 railway, we will be carrying out topsoil stripping in areas close to Gilson Road.
In order to complete this work safely, we will install three-way traffic lights along a short section of Gilson Road and within our existing site access, from Monday 3 July until Friday 14 July. The location of the traffic management is shown in the map below. The traffic lights will be in place from 9.30am until 3.30pm, Monday to Friday.