Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Offchurch
- Contractor
- BBV JV
- Type of works
- Traffic management, Vegetation clearance
- Estimated Start Date
- 15/07/2024
- Estimated End Date
- 23/08/2024
What we are doing
As we progress the construction of Welsh Road Overbridge and new road realignment, we need to complete the following works:
• Vegetation clearance of verges along a section of Welsh Road and installation of drainage
• Installing curbs and pavements to prepare the new road realignment
To ensure we can complete these works safely we will install temporary traffic lights. These works will be completed from 15 July to 23 August 2024. The temporary traffic lights will be in place 24 hours a day over this period.