Temporary traffic lights on Welsh Road, Offchurch

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-12-06/06/2024

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Offchurch
Contractor
BBV JV
Type of works
Traffic management, Vegetation clearance
Estimated Start Date
15/07/2024
Estimated End Date
23/08/2024

What we are doing

As we progress the construction of Welsh Road Overbridge and new road realignment, we need to complete the following works:
• Vegetation clearance of verges along a section of Welsh Road and installation of drainage
• Installing curbs and pavements to prepare the new road realignment

To ensure we can complete these works safely we will install temporary traffic lights. These works will be completed from 15 July to 23 August 2024. The temporary traffic lights will be in place 24 hours a day over this period.