Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-37-27/01/2025

Work Item Summary

Project Phase
Phase 2a
Region
Staffordshire
Location
Stone
Worksite Name
Yarnfield Lane
Contractor
Balfour Beatty
Type of works
hedgerow cutting
Estimated Start Date
19/02/2025
Estimated End Date
24/02/2025

What we are doing

As part of our ongoing maintenance of sites along Yarnfield Lane, we will be carrying out essential works to roadside hedgerows on Wednesday 19 February until Friday 21 February 2025 and Monday 24 February 2025.

These works are required to ensure the public highway remains clear and safe to use. We will need to install two-way temporary Traffic lights to ensure the safety of the workforce and road users during this time. If your journey is affected by these works, we appreciate your patience and understanding for any minor delay. We also urge you to allow additional time for your journey as necessary