Temporary traffic management on A453 Sutton Road and Drayton Lane

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-4-09/05/2023

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire, West Midlands
Location
Drayton Bassett
Contractor
BBV JV
Estimated Start Date
31/07/2023
Estimated End Date
11/08/2023

What we are doing

We need to undertake surveys that will record the underground drainage network. The information acquired from these surveys will
feed the design of the proposed new alignment of the A453 Sutton Road to accommodate the new high-speed railway.

To complete these works safely and efficiently we will install temporary traffic managementas follows:

  • Daytime lane closure with temporary traffic lights on A453 Sutton Road / Drayton Lane between 24 July to 28 July from 9.30am until 3.30pm.
  • Daytime closures of Drayton Lane between 31 July to 11 August from 9.30am until 3.30pm (Not including weekends)

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]