Temporary weekend road closures – Long Itchington Road
Work item: HS2 EW LM Ph1 Ar No N3 Prog works 25 06/10/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire, West Midlands
- Location
- Offchurch
- Contractor
- LM JV
- Type of works
- Road closure
- Estimated Start Date
- 04/09/2021
- Estimated End Date
- 19/09/2021
What we are doing
As part of the Fosse Way highway realignment scheme, LM will be temporarily closing a section of Long Itchington Road (National Cycle
Rte. 41) over three weekends in September from 8.00am on Saturday through to 6.00pm on Sunday. The reason for each closure is to install utility crossings. The dates of the closures are as follows:
- Saturday 4 and Sunday 5 September
- Saturday 11 and Sunday 12 September
- Saturday 18 and Sunday 19 September
Access will still be maintained for pedestrians, cyclists, households and businesses along the route and a clearly signposted diversion will be in place. All works are subject to consent, site, and weather conditions.