Thames Water work on Grafton Crescent, NW1 – 4 January to 16 April 2024

Work item: HS2-MW-UT-Ph1-Ca-S1-UT-16-01/12/2023

Work Item Summary

Project Phase
Phase 1
Region
Camden
Location
Grafton Crescent
Contractor
Thames Water
Type of works
Utility works / surveys
Estimated Start Date
04/01/2024
Estimated End Date
16/04/2024

What we are doing

Thames Water will install a protective tunnel lining to an existing raw water tunnel, to provide added structural stability during future underground HS2 works.

The main work will be undertaken within Barrow Hill reservoir site (for details follow this link), with the site on Grafton Crescent being required for emergency access only.

The work is expected to last from Thursday 4 January to Tuesday 16 April 2024.

We will monitor noise levels, but  do not expect to create high levels of noise as most activity will be carried out underground.

There will be a one lane closure and a one-way system operating in Grafton Crescent whilst we carry out the works.

Access will be from Castle Road with exits onto Castlehaven Road. Public footways will remain open. There will be two parking bay suspensions, one bay to the side of 117 Castlehaven Road and one bay to the side of 119 Castlehaven Road.

For all enquiries about the work Thames Water are doing on behalf of HS2, please use the below details and quote the reference number: 00346914.

Phone: 0800 316 9800 (our lines are always open) Email: [email protected]

For further details please see notification below.