Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Location
- Park Village East
- Contractor
- Thames Water
- Type of works
- Utility works / surveys
- Estimated Start Date
- 28/02/2022
- Estimated End Date
- 06/04/2022
What we are doing
Lorry lay-by install on Park Village East north – from 21 March to early May
- On 14 March we will install 16 new parking bays at the northern end of Park Village East, to replace the 14 parking bays in front of 6 to 16 Park Village East to make way for traffic to pass the lorry lay-by. We will need to temporarily suspend the parking bays in front of 2 to 28 Park Village East, from 14 to 15 March, to make way for these works.
- From 21 March to early May, we will install a 70m lorry lay-by within the footway and carriageway opposite 6 to 16 Park Village East.
- For safety, we will close the road at the northern end of Park Village East while we install the lay-by. Road will be closed during working hours, Monday to Friday 8am to 6pm, and open the road during evenings, weekends, and bank holidays to reduce the impact on residents.
- Vehicles will not be able to access Park Village East via Parkway junction while the road is closed and will instead be diverted via Albany Street, Robert Street and Stanhope Street or via Arlington Road, Delancey Street, Albert Street and Mornington Street. Access for businesses and residents to the northern end of Park Village East will be via Mornington Street bridge and Park Village East south. A traffic marshal will be onsite during working hours to assist resident vehicles passing the worksite.
For further details please refer to the notification ‘Lorry lay-by install on Park Village East north – from 21 March to early May’ below.