Work Item Summary
- Region
- Hillingdon, London
- Location
- Ickenham
- Contractor
- Thames Water
- Type of works
- Utility works / surveys
- Estimated Start Date
- 17/04/2023
- Estimated End Date
- 19/05/2023
What we are doing
Thames Water are nearing the completion of our work at the Ickenham Green allotments and the surrounding area. They are now in the process of reinstating work areas.
Between 17 April and 19 May Thames Water will remove the bell mouth of the temporary road off High Road leading to the allotment site.