Third party telecommunications work at the Adelaide Road site
Work item: HS2-EW-SCS-Ph1-Ar-So-S1-Prog-Works-1-09/12/2024
Work Item Summary
- Project Phase
- Phase 1
- Region
- Camden
- Worksite Name
- Adelaide Road Vent Shaft site
- Contractor
- Clarke Telecom
- Type of works
- Telecommunication works
- Estimated Start Date
- 06/01/2025
- Estimated End Date
- 20/01/2025
What we are doing
From 6 to 20 January 2025, Clarke Telecom will be upgrading their telephone mast and utility cabinet within the Adelaide Road Vent Shaft site. These works will take place Monday to Friday between 8am and 5pm.
To help these works take place, we will be providing Clarke Telecom temporary access to a section of the site which will allow them to do their works.
During these works you may notice the following activities:
- Clarke Telecom operatives on site
- Temporary welfare set up and removal
- Deliveries to site via the main gate on Adelaide Road
- Use of handheld and battery powered tools
- Work on Clarke Telecom’s mast
We do not anticipate these works to be noisy, but we will advise Clarke Telecom operatives to be mindful of the community when carrying out their works on our site.
Download information relating to these works
Find out more about