Skip to main page content
View route map

Tower crane base construction, Mandeville Road Vent Shaft site

Work item: HS2-EW-SCS-Ph1-Ar-So-S2-Prog-Works-1-30/10/2024

Work Item Summary

Project Phase
Phase 1
Region
Brent and Ealing
Location
Mandeville Road
Worksite Name
Mandeville Road
Contractor
SCS JV
Type of works
Concrete break out, Concrete pours
Estimated Start Date
18/11/2024
Estimated End Date
20/12/2024

What we are doing

What we are doing
From 18 November to 20 December 2024, we will be clearing an area on site to build a concrete base for a tower crane due to arrive in January 2025.

A saw will be used to cut up the concrete surface and an excavator will then be used to break out the remainder of the platform. This will create some noise and vibration; we will minimise the breaking as much as possible.

To create the new base, we will dig down one metre and refill with concrete. Concrete will be delivered within core working hours. We will use an excavator and a vibrating plate. You may experience increased construction noise and vibration during these works.

Noise and vibration monitoring will be in place during the works. We will use water sprays to reduce dust and noise barriers around the machinery to help reduce noise. We would like to apologise in advance for any disruption or inconvenience this may cause.

For further details please find the link to the notification below.

Download information relating to these works

Find out more about

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]