Updated notice of traffic management and closure of Stoneleigh Road and Stareton Lane, Stoneleigh
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-44-13/07/2023
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Stoneleigh
- Contractor
- BBV JV
- Type of works
- Piling, Road closure
- Estimated Start Date
- 14/08/2023
- Estimated End Date
- 08/09/2023
What we are doing
Updated notice
Traffic lights will be operational throughout the duration of the works
To complete the re-alignment works of Stareton Lane, a section of Stareton Lane will be closed. To carry out the piling works for the new Stoneleigh Road overbridge and complete surfacing and lining works on the new Stareton Lane junction, we will require multi -way temporary traffic lights, and a section of Stoneleigh Road will need to be closed.
Stareton Lane will be closed from 14 August to 8 September 2023, with a diversion please refer to Map 1.
Stoneleigh road will have overnight temporary lights in place from 18 August to 4 September 2023 from 8pm to 8am, please refer to Map 2.
Stoneleigh Road will be closed from 4 to 8 September 2023, with a diversion please refer to Map 3.
Access to all properties will be maintained. Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]