Updated notice of traffic management and closure of Stoneleigh Road and Stareton Lane, Stoneleigh

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-44-13/07/2023

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Stoneleigh
Contractor
BBV JV
Type of works
Piling, Road closure
Estimated Start Date
14/08/2023
Estimated End Date
08/09/2023

What we are doing

Updated notice

Traffic lights will be operational throughout the duration of the works

To complete the re-alignment works of Stareton Lane, a section of Stareton Lane will be closed. To carry out the piling works for the new Stoneleigh Road overbridge and complete surfacing and lining works on the new Stareton Lane junction, we will require multi -way temporary traffic lights, and a section of Stoneleigh Road will need to be closed.

Stareton Lane will be closed from 14 August to 8 September 2023, with a diversion please refer to Map 1.

Stoneleigh road will have overnight temporary lights in place from 18 August to 4 September 2023 from 8pm to 8am, please refer to Map 2.

Stoneleigh Road will be closed from 4 to 8 September 2023, with a diversion please refer to Map 3.
Access to all properties will be maintained. Our workforce maybe on site one hour before and one hour after to set up and secure our equipment.