Traffic management on A4091, Middleton
Work item: HS2-MW-OTH-Ph1-Ar-No-N2-Prog-works-5-07/04/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Middleton
- Contractor
- South Staffs Water
- Type of works
- Enabling works
- Estimated Start Date
- 04/07/2022
- Estimated End Date
- 05/08/2022
What we are doing
South Staffs Water will be carrying out the diversion of an existing water main. All works will be undertaken within the carriageway of the A4091, Middleton. All accesses will be maintained with the use of 3-way temporary traffic lights on A4091 and Bodymoor Heath Road.
The work is planned to start on 4 July 2022 and is expected to last until 5 August 2022. All works will be undertaken between the hours of 8.00am to 5.00pm Monday to Friday.