Traffic management on A4091 Tamworth Road, Middleton

Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-07-14/01/2022

Work Item Summary

Project Phase
Phase 1
Region
Warwickshire
Location
Middleton
Contractor
BBV JV
Type of works
Survey, Traffic management
Estimated Start Date
04/04/2022
Estimated End Date
07/04/2022

What we are doing

We will be carrying out a number of surveys on and around the carriageway of the A4091. To complete the surveys a team of engineers will visit the location to record what is present in the area and carry out trial trenching, which will involve digging into the ground to establish what is underneath the surface. This will provide us with information which we need to assess as we develop our construction plans.

When these works will take place
These works will take place between 4 to 7 April from 9.30 am to 3.30 pm. To complete these works safely we will install the following traffic management on the A4091:
4 April Single lane closure on southbound dual carriageway section
5 & 6 April Full northbound dual carriageway closure
7 April Two-way traffic lights on single lane section