Traffic management on A4091 Tamworth Road, Middleton
Work item: HS2-MW-BBV-Ph1-Ar-No-N2-Traf-07-14/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Middleton
- Contractor
- BBV JV
- Type of works
- Survey, Traffic management
- Estimated Start Date
- 04/04/2022
- Estimated End Date
- 07/04/2022
What we are doing
We will be carrying out a number of surveys on and around the carriageway of the A4091. To complete the surveys a team of engineers will visit the location to record what is present in the area and carry out trial trenching, which will involve digging into the ground to establish what is underneath the surface. This will provide us with information which we need to assess as we develop our construction plans.
When these works will take place
These works will take place between 4 to 7 April from 9.30 am to 3.30 pm. To complete these works safely we will install the following traffic management on the A4091:
4 April Single lane closure on southbound dual carriageway section
5 & 6 April Full northbound dual carriageway closure
7 April Two-way traffic lights on single lane section
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]