Traffic Management on Drayton Lane, Drayton Bassett
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-14-14/03/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Drayton Bassett
- Contractor
- BBV JV
- Type of works
- Construction, Haul road construction, Plant crossing, Traffic management
- Estimated Start Date
- 25/07/2022
- Estimated End Date
- 16/09/2022
What we are doing
We are constructing haul roads and accesses within Drayton Bassett. To allow our vehicles to cross Drayton Lane and to maintain the safety of road users, equestrian and pedestrians, we will create a signalised plant crossing. To enable us to commence these works we will require a temporary closure of a section of Drayton Lane.
We will complete these works in two phases from 25 July to 16 September which will require closures of a section of Drayton Lane towards the end of these works.
Download information relating to these works
Find out more about
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]