Traffic management on Gilson Road, nr Coleshill
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-49-18/01/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Gilson
- Contractor
- BBV JV
- Type of works
- Traffic management, Vegetation clearance
- Estimated Start Date
- 04/04/2022
- Estimated End Date
- 23/04/2022
What we are doing
BBV will complete vegetation clearance works in areas near Gilson Road. The works will be completed in preparation for construction of the railway. All necessary permits will be in place prior to works being
complete and where necessary, ecological surveys will be conducted prior to and during the works.
The vegetation clearance works will take place from Monday 4 April until Saturday 23 April.
In order for us to carry out works close to Gilson Road safely, we will install a temporary two-way traffic light system here from Monday 18 April until Saturday 23 April.