Traffic management on Sutton Road and Drayton Lane, Drayton Bassett

Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Traf-16-14/03/2022

Work Item Summary

Project Phase
Phase 1
Region
Staffordshire
Location
Drayton Bassett
Contractor
BBV JV
Type of works
Survey, Traffic management
Estimated Start Date
01/08/2022
Estimated End Date
03/08/2022

What we are doing

We will be carrying out utilities’ surveys on and around the carriageway of Sutton Road / A453. To complete the surveys a team of engineers will visit the location to record what is present in the area and carry out trial trenching, which will involve digging into the ground to establish what is underneath the surface. This will provide us with information which we need to assess as we develop our construction plans.

These works will take place from 1 August to 3 August between 9.30am to 3.30pm. During this period, we will have temporary traffic lights in place.