View route map
Traffic management on the A5 Hints Bypass
Work item: HS2-EW-LM-Ph1-Ar-No-N2-Traf-1-01/11/2021
Work Item Summary
- Project Phase
- Phase 1
- Region
- Staffordshire
- Location
- Hints
- Contractor
- LM JV
- Type of works
- Traffic management, Vegetation clearance
- Estimated Start Date
- 12/04/2021
- Estimated End Date
- 15/04/2021
What we are doing
There will be lane closures in place on the A5 Hints Bypass between the Weeford Interchange and the A452 Sutton Road. These works follow similar works in early 2021. These will allow safe access to our work sites to prepare for future construction works, which include roadside vegetation clearance. The lane closures will be in place from 9.30am to 3.30pm daily between Monday 12 April and Thursday 15 April.
Download information relating to these works
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email [email protected]