Traffic management on the M42 and M6 Toll, Coleshill
Work item: HS2-MW-BBV-Ph1-Ar-No-N1-Prog-works-1-20/07/2022
Work Item Summary
- Project Phase
- Phase 1
- Region
- Warwickshire
- Location
- Coleshill
- Contractor
- BBV JV
- Estimated Start Date
- 05/09/2022
- Estimated End Date
- 10/09/2023
What we are doing
The work we will be completing
We previously sent out a notification outlining three phases of traffic management on the M42 and M6 Toll from Monday 5 September to complete work on the M42 Triple Box Structure. Due to unforeseen circumstances, our traffic management will now only take place in one phase from Monday 5 September until Saturday 10 September.
We will be starting work on Monday 5 September
Our works will now only take place from Monday 5 September until Saturday 10 September from 8pm to 5am: northbound and
southbound lane closure on the M42 and M6 Toll. During this time there will be a southbound diversion in place. The traffic management will be in place overnight from 8pm until 5am.